Some industrial projects reach the end of the preliminary study with everything approved: feasibility confirmed, design finalised, budget adjusted. And yet construction does not start on the planned date. Something has got stuck along the way.
A design decision limits what can be applied for in the licence. A poorly resolved sizing forces corrections once works are already under way. And when several suppliers work without a shared vision, each one resolves its own part without knowing how it fits with the others.
Could all of this have been known earlier? Yes. But someone would have had to review the project with a protocol that detects those friction points before they reach the site, not once they have already halted the work. Let us see how.
Why a project that looks clear on paper stalls before it starts
For us at ALTERTECNIA, the key lies in reviewing feasibility, design and technical definition before the project moves on to the next phase.
That protocol starts from the idea that all these aspects, plus licences and site coordination, are phases of a single process. The problem is that they are not always treated that way, so each one has its own owner and its own pace, as if they did not depend on one another.
Each supplier moves forward with the information it has. Nobody checks whether its part fits with everyone else's.
That is why we say that bottlenecks, in most cases, do not stem from a one-off error, but from the lack of a vision that connects every phase from the very start of the project.
Feasibility and design: the stage with the most room for decision-making
Feasibility is the first question that should be answered, and it is the one most often taken for granted. Checking square metres or budget is not enough. You have to confirm that the industrial building can accommodate the intended activity, with its processes, its machinery and its specific technical requirements.
When that analysis is skipped or done superficially, the problem appears later on, sometimes months afterwards, with an investment already committed.
Something similar happens with design. A layout may solve the distribution well on the drawing and still fail the first serious review before the works go out to tender. Many errors are detected when checking whether that design can be processed and built without surprises:
- a distribution that does not respect the setbacks or separation distances required by the activity
- a sizing that does not match the actual machinery and forces the project to be redone before tendering the works
- a growth forecast that was not considered and blocks any future extension
>> You may be interested in: Quality in industrial installations: the critical points that are resolved at design stage.
The later one of these problems is detected, the more resources are already committed and standing idle: if it appears in the preliminary study nothing has been contracted, but if it appears on the eve of the licence or the works, there is already budget set aside, deadlines signed with suppliers and, sometimes, staff waiting to start.
That is why feasibility, design and technical design carry so much weight. It is the stage where things can still be redirected without stopping the works or redoing what has been built.
Licences on time
Licences are usually treated as a formality triggered once the project is already closed, rather than as a task that should be part of the design from the outset. That is why they arrive late and lead to last-minute adjustments.
Bringing that work forward makes it possible to anticipate requirements and prevent the approval process from becoming a bottleneck just before construction begins. At ALTERTECNIA we have already discussed the effects that a delay in granting the licence has on a construction project, because it is one of the factors that wastes the most time when it is not managed in good time.
Coordination and single management
When several installation contractors work without a management that unifies criteria, each one may solve its own part well and yet the whole does not fit together. Nobody has checked how the different installations relate to one another.
That lack of common management causes delays and wastes resources that had already been planned, because correcting on the fly always costs more than having coordinated it from the beginning.
Commissioning: the proof that the project was conceived as a whole
If everything has been done in the right order and with the necessary checks, commissioning is the moment when all the previous decisions fit together.
At ALTERTECNIA we approach every industrial project with that overall vision, from the first feasibility analysis to the final coordination of the works. This way we reduce improvisation and give clients more control over their project from the start.
If you are considering an extension, a new facility or an opening and want to review the starting point before moving forward, get in touch with our team. We can help you detect bottlenecks before they appear.